Sample Timeline
TUESDAY, MARCH 1
Noon
New furniture and equipment on location
4:00 pm
Take up modular carpet and access floor panels.
5:00 pm
Locate data/com cables and reroute to workstations
5:30 pm
Install service boxes in floor and convert to Powerflex modular systems.
7:00 pm
Install data/com access
8:30 pm
Close up floor
9:30 pm
Install modular furniture for new workstations
Midnight
Install phones, PCs, printers, and copier.
WEDNESDAY, MARCH 2
8:00 am
Existing staff arrives, resumes work
9:00 am
New staff moved in and functioning
|