Sample Timeline

TUESDAY, MARCH 1
Noon
New furniture and equipment on location

4:00 pm
Take up modular carpet and access floor panels.

5:00 pm
Locate data/com cables and reroute to workstations

5:30 pm
Install service boxes in floor and convert to Powerflex modular systems.

7:00 pm
Install data/com access

8:30 pm
Close up floor

9:30 pm
Install modular furniture for new workstations

Midnight
Install phones, PCs, printers, and copier.


WEDNESDAY, MARCH 2

8:00 am
Existing staff arrives, resumes work

9:00 am
New staff moved in and functioning

Powerflex Xcel
Modular Components

Typical Service Reconfiguration Timeline
Cable Management
Cablematrix Planning Service
Specifications and Testing

Typical Reconfiguration Timeline

Reconfiguring your space can now happen overnight!

Tuesday, March 1 | Noon

Add copier, fax unit, and network printing station.

• Add dedicated outlet for copier
• Add 6 normal power outliets
• Tie 3 printers to LAN

See Cablematrix plan for new service requirements and access module locations on floor.

Add 6 new customer service stations.

• 6 phone access
• 6 LAN access
• 6 dedicated LAN power outlets
•18 normal power outlets

Install standard unit supervisor station.

• phone access
• LAN access
• LAN power
• dedicated outlet
• 3 normal power outlets


Wednesday, March 2 | 8:00am

8:00 am | Existing staff arrives, resumes work

9:00 am | New staff moved in and functioning